1. Introduction
Government of India have launched the Pradhan Mantri Gram Sadak Yojana on 25th December, 2000 to provide all-weather access to unconnected habitations.  Pradhan Mantri Gram Sadak Yojana (PMGSY) is a 100% Centrally Sponsored Scheme
2. Programme Objectives
The primary objective of the PMGSY is to provide Connectivity, by way of an all-weather road (with necessary culverts and cross-drainage structures), to the eligible unconnected Habitations in the rural areas.

Web Site :- Detal information of PMGSY in Latur District is available on http://pmgsyonline.nic.in/Citizens/en/DIST/05DP/DistrictProfile.asp?state=MH&district=16

Works Completed & Ongoing Works

PMGSY ABSTRACT  PHASE II TO VIII
PMGSY. Progress Report  Dist. Latur Upto Date  30 / 04 /2010
Sr. No. Phase Package No. Programme Year No.of Works Sanctioned Length in Km. Tendered Amount   in Lakh Received Grants up to 30.04.2010in Lakh No.of work Completed Total Expenditure  upto 2007-08 in Lakh  Expenditure in 2008-09        in Lakh  Expenditure in 2009-10        in Lakh  Total Expenditure upto 30.04.2010        in Lakh Remark
Up to    3/2006 2006-07 2007-08 2008-09 2009-10 Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1 II MH 16-02 2001-03 9 26.60 279.48 650.00 0.00 0.00 0.00 0.00 650.00 9 291.48 0.00 0.00 291.48 All works Completed & Final Payment made
2 II MH 16-03 2001-03 11 21.64 277.58 0.00 11 278.23 0.00 0.00 278.23
3 III MH 16-04 2003-04 9 22.01 252.29 236.79 13.85 0.00 0.00 0.00 250.64 9 242.78 0.00 0.00 242.78
4 IV MH 16-05 2004-05 4 9.95 121.51 41.80 0.38 0.00 0.00 0.00 42.18 4 122.47 0.00 0.00 122.47
5 V MH 16-06 to 15 2005-06 59 141.51 2285.73 0.00 750.00 0.00 0.00 0.00 750.00 59 2158.42 0.00 49.48 2207.90 All  Works Completed 
6 VI MH 16-16 to 25 2006-07 10 130.63 3692.53 0.00 0.00 0.00 3507.84 0.00 3507.84 10 0.00 2643.86 826.97 3470.83 All works  Completed
7 VII MH 16-26 to 31 2007-08 22 108.40 2712.52 0.00 0.00 0.00 0.00 1125.00 1125.00 0 0.00 0.00 811.00 1079.37 All Works are in Progress
8 VIII MH 16-32 to 41 2008-09 18 78.38 2318.18 0.00 0.00 0.00 0.00 345.00 345.00 0 0.00 0.00 113.14 164.07 All Works are in Progress
    Total   142 539.12 11939.82 928.59 764.23 0 3507.84 1470.00 6670.66 102 3093.38 2643.86 1800.59 7857.13  

 

PRADHAN MANTRI GRAM SADAK YOJANA  2010-11
Form : 7
Name of State : MAHARASHTRA Phase : VII
   State Code : MH-16 Month : April 2010
SR.No. Name of Block Package No. Name of Road Sanctioned Cost (Rs. in Lakhs) Length (In Kms) Date of Work Order (dd/mm/yy) Name of Contractor Stipulated Date of Completion
1 4 5 6 7 8 10 11 11
1 Ausa MH-16-26 Ausa - Sarola (T16) 204.95 9.5 24-08-2009 M/S Minar Construction Latur 24-08-2010
2 Ausa MH-16-26 Nagarsoga - Talni (T14) 256.35 13.8 24-08-2009 24-08-2010
3 Nilanga MH-16-27  MDR-31 To Sitaphalwadi ( L-092) 52.93 2.20 20-07-2009 Shri S.N Khatib Const. Nilanga 20-07-2010
4 Nilanga MH-16-27 SH-167 To Machratwadi ( L-061) 59.57 2.40 20-07-2009 20-07-2010
5 Nilanga MH-16-27  SH--167 To Bujrugwadi( L-080) 40.29 1.80 20-07-2009 20-07-2010
6 Nilanga MH-16-27 ODR-83 To Ambegaon(M.) L-082 20.51 1.02 20-07-2009 20-07-2010
7 Nilanga MH-16-27  ODR-83 Rathoda tanda To rathoda Road( L-079) 100.93 4.40 20-07-2009 20-07-2010
8 Nilanga MH-16-27  SH-166(kavthapati) To Gouar (L-085) 70.76 2.75 20-07-2009 20-07-2010
9 Nilanga MH-16-27  SH-165 To Makani To Chanachiwadi( L-041) 175.1 6.50 20-07-2009 20-07-2010
10 Nilanga MH-16-27  Jajnoor To Jajnoor Zopadpatti (L-076) 85.76 3.60 20-07-2009 20-07-2010
11 Shirur Anantpal MH-16-27 Hippalgaon - Sawargaon( L049) 76.69 2.7 18-07-2009 18-07-2010
12 Deoni MH16-28 Bombli - Korewadi (L039) 84.65 2.27 14-07-2009 Shri B.R .Andhe Latur 14-07-2010
13 Udgir MH16-28 SH-168 - Shirol Janapur to State Border (T04) 179.27 12.00 14-07-2009 14-07-2010
14 Udgir MH16-28 SH-17 - Dongraj (T13) 253.37 7.84 14-07-2009 14-07-2010
15 Ahmadpur MH16-29 SH-156 Ugilewadi Sawargaon Rokda to Himpalner road (T11/T16) 284.68 11.52 18-07-2009 M/s Rohini Construction Ahmadpur 18-07-2010
16 Chakur MH16-30 MSH-3 To Mohanal (L-067) 36.12 1.37 28-07-2009 Rudrani Infrastructure Pvt.Ltd.Aurangabad 28-07-2010
17 Chakur MH16-30 MDR-19 to Shivni Majara (L061) 67.86 1.1 28-07-2009 28-07-2010
18 Chakur MH16-30  Zari to Ganesh Nagar, Fattu Naiek Tanda (L061) 92.2 2.87 28-07-2009 28-07-2010
19 Renapur MH16-31 Karepur to VR 16       (L0-35) 64.78 2.97 23-07-2009 M/s Vaishali Construction Latur  28-07-2010
20 Renapur MH16-31 S.H.144 to Darjiborgaon, Indarthana (T0-11) 249.4 9.24 23-07-2009 23-07-2010
21 Latur MH16-31 M.D.R. 10 to Raiwadi, Nandgaon( L0-63) 106.63 3.95 23-07-2009 23-07-2010
22 Latur MH16-31 M.D.R. 10 to Shiur      (L0-34) 35.68 2.6 23-07-2009 23-07-2010
Total 2598.48 108.4 …… ….. ……
PRADHAN MANTRI GRAM SADAK YOJANA  2010-11
                                                                                                                  "PROGRESS REPORT" (Form 8 )
Name of State : MAHARASHTRA Phase : VII
State Code : MH-16 Month : April 2010
Sr. No. Name of District District Code Name of Block Package No Name of Road Road Length U / N Sanctioned Cost (Rs. in Lakhs) Value of Work done Rs. In lakh Payment Made In Remarks
Up to Last Month During This Month Total Up to Last Month During This Month Total
1 2 3 4 6 7 8 9 10 11 12 13 14 15 16 17
1 Latur 16 Ausa MH-16-26 Ausa - Sarola (T16) 9.5 U 204.95 74.54 0.00 174.17 74.54 0.00 174.17 Carpet in Progress
2 Latur 16 Ausa MH-16-26 Nagarsoga - Talni (T14) 13.8 U 256.35 17.77 0.00 148.09 17.77 0.00 148.09 Carpet in Progress
3 Latur 16 Nilanga MH-16-27 Upgradation to MDR-31 To Sitaphalwadi ( L-092) 2.20 U 52.93 11.22 0.00 11.22 11.22 0.00 11.22 MPM in progress
4 Latur 16 Nilanga MH-16-27 Upgradation to SH-167 To Machratwadi ( L-061) 2.40 U 59.57 20.76 0.00 20.76 20.76 0.00 20.76 MPM in progress
5 Latur 16 Nilanga MH-16-27 Upgradation to SH--167 To Bujrugwadi( L-080) 1.80 U 40.29 0.50 0.00 0.50 0.50 0.00 0.50 MPM in progress
6 Latur 16 Nilanga MH-16-27 Upgrdation To ODR-83 To Ambegaon(M.) L-082 1.02 U 20.51 3.96 0.00 3.96 3.96 0.00 3.96 MPM in progress
7 Latur 16 Nilanga MH-16-27 Upgrdation To ODR-83 Rathoda tanda To rathoda Road( L-079) 4.40 U 100.93 22.91 0.00 22.91 22.91 0.00 22.91 MPM in progress
8 Latur 16 Nilanga MH-16-27 Upgradation To SH-166(kavthapati) To Gouar (L-085) 2.75 U 70.76 12.91 0.00 23.79 12.91 0.00 23.79 MPM in progress
9 Latur 16 Nilanga MH-16-27 Upgradation To SH-165 To Makani To Chanachiwadi( L-041) 6.50 U 175.1 33.71 0.00 65.18 33.71 0.00 65.18 MPM in progress
10 Latur 16 Nilanga MH-16-27 Upgradation To Jajnoor To Jajnoor Zopadpatti (L-076) 3.60 U 85.76 30.95 0.00 30.95 30.95 0.00 30.95 MPM in progress
11 Latur 16 Shirur Anantpal MH-16-27 Hippalgaon - Sawargaon( L049) 2.7 U 76.69 7.57 0.00 31.59 7.57 0.00 31.59 MPM in progress
12 Latur 16 Deoni MH16-28 Bombli - Korewadi (L039) 2.27 U 84.65 21.35 0.00 67.61 21.35 0.00 67.61 Carpet in Progress
13 Latur 16 Udgir MH16-28 SH-168 - Shirol Janapur to State Border (T04) 12.00 U 179.27 79.72 0.00 126.13 79.72 0.00 126.13 Carpet in Progress
14 Latur 16 Udgir MH16-28 SH-17 - Dongraj (T13) 7.84 U 253.37 60.04 0.00 169.54 60.04 0.00 169.54 Arch Bridge & Carpet in Progress
15 Latur 16 Ahmadpur MH16-29 SH-156 Ugilewadi Sawargaon Rokda to Himpalner road (T11/T16) 11.52 U 284.68 20.83 0.00 98.64 20.83 0.00 98.64 MPM in progress
16 Latur 16 Chakur MH16-30 Upgradation to MSH-3 To Mohanal (L-067) 1.37 U 36.12 5.85 0.00 10.43 5.85 0.00 10.43 MPM in progress
17 Latur 16 Chakur MH16-30 Upgradation toMDR-19 to Shivni Majara (L061) 1.1 U 67.86 25.05 0.00 47.04 25.05 0.00 47.04 Arch Bridge & Carpet in Progress
18 Latur 16 Chakur MH16-30 Upgrdation of Zari to Ganesh Nagar, Fattu Naiek Tanda (L061) 2.87 U 92.2 29.25 0.00 39.64 29.25 0.00 39.64 MPM in progress
19 Latur 16 Renapur MH16-31 Karepur to VR 16       (L0-35) 2.97 U 64.78 5.77 0.00 43.85 5.77 0.00 43.85 Carpet in Progress
20 Latur 16 Renapur MH16-31 S.H.144 to Darjiborgaon, Indarthana (T0-11) 9.24 U 249.4 13.98 0.00 82.92 13.98 0.00 82.92 MPM in progress
21 Latur 16 Latur MH16-31 M.D.R. 10 to Raiwadi, Nandgaon( L0-63) 3.95 U 106.63 14.10 0.00 18.91 14.10 0.00 18.91 MPM in progress
22 Latur 16 Latur MH16-31 M.D.R. 10 to Shiur      (L0-34) 2.6 U 35.68 6.51 0.00 17.26 6.51 0.00 17.26 MPM in progress
          Total 108.4   2598.48 519.25 0.00 1255.09 519.25 0.00 1255.09  
PRADHAN MANTRI GRAM SADAK YOJANA  2010-11
                                                                                                       Form : 7
    Name of State : MAHARASHTRA Phase: VIII
   State Code : MH-16 Month : April 2010
Sr.No Block Package Name of Road (U/N) Sanctioned Cost Rs. In Lakhs Length in [Kms] Date Of Work Order Name Of Contractor Stipulated Date Of Compleation
1 Ausa MH1632 Ekambi Tanda - Chincholi K( L021) U 255.58 8.86 14-12-2009 Dhanchandra Construction Latur 14-12-2010
2 Ausa MH1632 Boaregaon - Kawatha Kej ( L071) U 14.2 0.6
3 Nilanga MH1633 Upgradation To SH-167 To Chandori. (L-042) U 250.94 12.12 10-12-2009 M/s Minar Constuction Latur 10-12-2010
4 Nilanga MH1634 Upgradation to SH-167 To Dongargaon(H.)        (T-12) U 230.73 10.32 11-12-2009 M/s Bhavani Const. 11-12-2010
5 Nilanga MH1635 Upgrdation To Sh-163 to Mirganhalli( L-054) U 31.3 1.10 21-12-2009 Shri.S.N Khatib Cons.& Co.Nilanga 21-12-2010
6 Nilanga MH1635 Upgradation to SH-167 To Sabitwadi  (L-052) U 61.36 2.25
7 Nilanga MH1635 Upgradation To SH-163 To Mudgadwadi (L-059) U 14.71 0.60
8 Deoni MH1636 MDR-25 - Kumdal (H) (L050) U 26.8 0.84 11-12-2009 Reddy Const.Latur 11-12-2010
9 Deoni MH1636 SH166 - Sangam (L027) U 83.81 1.2
10 Udgir MH1636 T-13 - Hanmuntwadi (L066) U 80.88 2.65
11 Udgir MH1636 T-13 - Karlewadi , Wanjarwadi( L068) U 26.35 0.96
12 Udgir MH1637 Pir Tanda - Dongarshelaki Tanda (L081) U 82.75 2.6 10-12-2009 Shri.B.R.Andhe  10-12-2010
13 Jalkot MH1637 Dist. Border Umerdara Wanjarwad to SH-225 (T10) U 157.51 6.5
14 Ahmadpur MH1638 MDR-38 Tirth Dhanora Unni Hippalgaon Hadolti road (T02) U 354.81 11.5 22-12-2009 B.S.Pawar Latur 22-12-2010
15 Ahmadpur MH1639 MSH-3 Shenni Anandwadi road (L099) U 77.29 2.8 12-12-2009 Rohini Construction Ahamadpur 12-12-2010
16 Renapur MH1640 S.H.144 to Jawalga,Selu( T0-3) U 348.48 9.16 09-12-2009 M/s Ashirwad Construction Garsuli Tq. Latur. 09-12-2010
17 Latur MH1641 O.D.R-20 to Khulgapur (L0-69) U 82.87 3.09 12-12-2009 Reddy Const.Latur 12-12-2010
18 Latur MH1641 MSH-3 to Sikandarpur(L0-29) U 30.67 1.23
Total   2211.04 78.38 …. …. ….
                                                                           PRADHAN MANTRI GRAM SADAK YOJANA 2010-11
                                                                                           "PROGRESS REPORT" (Form 8 )
Phase: VIII
Name of State : MAHARASHTRA Month : April 2010
                      State Code : MH-16
Sr. No. Name of District District Code Name of Block Package No Name of Road Road Length U / N Road No Sanctioned Cost Rs. In Lakhs Value of Work done Rs. In lakh Payment Made In Remarks
Up to Last Month During This Month Total Up to Last Month During This Month Total
1 2 3 4 6 7 8 9 10 11 12 13 14 15 16 17 18
1 Latur 16 Ausa MH1632 Ekambi Tanda - Chincholi K( L021) 8.86 U 1 255.58 0.00 50.93 50.93 0.00 50.93 50.93 Box Cell Bridge & WBM Progress
2 Latur 16 Ausa MH1632 Boaregaon - Kawatha Kej ( L071) 0.6 U 2 14.2 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
3 Latur 16 Nilanga MH1633 Upgradation To SH-167 To Chandori. (L-042) 12.12 U 1 250.94 0.00 0.00 0.00 0.00 0.00 0.00 MPM in Progress
4 Latur 16 Nilanga MH1634 Upgradation to SH-167 To Dongargaon(H.)        (T-12) 10.32 U 1 230.73 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
5 Latur 16 Nilanga MH1635 Upgrdation To Sh-163 to Mirganhalli( L-054) 1.10 U 1 31.3 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
6 Latur 16 Nilanga MH1635 Upgradation to SH-167 To Sabitwadi  (L-052) 2.25 U 2 61.36 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
7 Latur 16 Nilanga MH1635 Upgradation To SH-163 To Mudgadwadi (L-059) 0.60 U 3 14.71 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
8 Latur 16 Deoni MH1636 MDR-25 - Kumdal (H) (L050) 0.84 U 1 26.8 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
9 Latur 16 Deoni MH1636 SH166 - Sangam (L027) 1.2 U 2 83.81 0.00 0.00 0.00 0.00 0.00 0.00 Box Cell Bridge & WBM Progress
10 Latur 16 Udgir MH1636 T-13 - Hanmuntwadi (L066) 2.65 U 3 80.88 0.00 0.00 0.00 0.00 0.00 0.00 WBM work & CD woek in Progress
11 Latur 16 Udgir MH1636 T-13 - Karlewadi , Wanjarwadi( L068) 0.96 U 4 26.35 0.00 0.00 0.00 0.00 0.00 0.00 Earth work in Progress
12 Latur 16 Udgir MH1637 Pir Tanda - Dongarshelaki Tanda (L081) 2.6 U 1 82.75 0.00 0.00 0.00 0.00 0.00 0.00 Earth work in Progress
13 Latur 16 Jalkot MH1637 Dist. Border Umerdara Wanjarwad to SH-225 (T10) 6.5 U 2 157.51 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
14 Latur 16 Ahmadpur MH1638 MDR-38 Tirth Dhanora Unni Hippalgaon Hadolti road (T02) 11.5 U 1 354.81 0.00 0.00 0.00 0.00 0.00 0.00 Earth work ,CD works in Progress
15 Latur 16 Ahmadpur MH1639 MSH-3 Shenni Anandwadi road (L099) 2.8 U 1 77.29 0.00 0.00 0.00 0.00 0.00 0.00 WBM in progress
16 Latur 16 Renapur MH1640 S.H.144 to Jawalga,Selu( T0-3) 9.16 U 1 348.48 113.14 0.00 113.14 113.14 0.00 113.14 Earth work ,CD works in Progress
17 Latur 16 Latur MH1641 O.D.R-20 to Khulgapur (L0-69) 3.09 U 1 82.87 0.00 0.00 0.00 0.00 0.00 0.00 MPM completed
18 Latur 16 Latur MH1641 MSH-3 to Sikandarpur(L0-29) 1.23 U 2 30.67 0.00 0.00 0.00 0.00 0.00 0.00 MPM completed
            78.38 0 30 2211.04 113.14 50.93 164.07 113.14 50.93 164.07